Require a written definition of 'A+ grade'

When a quotation simply says “A+ grade, 580 W”, key commercial and technical terms remain undefined. Ask the supplier to put its grade definition in writing with measurable acceptance criteria: what visual imperfections are permitted, what power tolerance applies, whether the modules are new, and which exact model code, bill of materials and warranty apply.

Ask the seller to define and support the “A+” description in writing. The label itself is not proof that the product holds a particular certification. A workable purchase file links a specific module model to valid test evidence, the serial numbers in your shipment and the legal entity standing behind the warranty.

Match the exact model code to the certificate scope

Write the full model code, rated output, module dimensions, connector type and key electrical ratings into the purchase contract. Request the datasheet, relevant certificates, the accompanying model list or scope annex, and underlying test reports. Check the named manufacturer and production site, and verify certificate numbers directly with the issuing body where possible.

A certificate may cover a module family rather than printing every individual power bin on the cover page. Have the issuing body or a qualified technical reviewer confirm that the exact model and construction you are ordering fall within the certified scope. A recognisable certification mark on a PDF is not proof on its own, and any discrepancy in model naming should be resolved before paying a deposit.

IEC 61215-1:2021 covers terrestrial photovoltaic module design qualification; its abstract explicitly notes that passing these tests does not provide a quantitative prediction of module lifetime. IEC 61730-1:2023 sets out requirements for safe module construction, while Part 2 covers testing. Neither standard turns a commercial grade label into proof that your specific shipment passed pre-shipment inspection.

What each document proves—and what it leaves open

Document or recordWhat to verifyWhat it does not prove on its own
Datasheet and signed specificationExact model code, electrical ratings, dimensions and agreed tolerancesWhether the manufactured batch matches the paperwork
Certificate scope and test reportsIssuing body, covered models and construction, and standard editions usedThe condition of individual shipped modules or guaranteed field lifespan
Serial-number and packing listsTraceability linking the purchase order, pallet numbers and individual module serialsElectrical output or absence of handling damage
Factory flash-test recordsModule serials, measured output, test conditions, equipment and calibration informationActual annual energy yield at the installation site
EL images, where contractedSerial-to-image matching, production stage when taken and review by a qualified specialist against agreed criteriaCompliance with all other electrical or safety checks
Written warranty documentWarrantor legal entity, coverage period, exclusions and claim procedureWho pays international freight or site labour unless explicitly stated

Tie pre-shipment inspection to the actual batch

Set the inspection protocol before production finishes: which checks apply to the full batch, which rely on sampling, how the inspector draws the sample and what happens if defects exceed the agreed limit. No single sample percentage fits every order; work out the sampling plan with your inspector based on order volume, supplier track record and project risk.

Visual checks should follow the criteria attached to your contract, covering front glass, frames, nameplates, junction boxes, cables, connectors and carton or pallet labelling. Electroluminescence (EL) imaging allows a trained reviewer to spot micro-cracks and connection defects that remain invisible to the naked eye; IEA PVPS outlines how IR and EL imaging work in practice. Make sure every EL image is indexed to a module serial number rather than accepting an unlabelled folder of undated files.

Cross-check the factory flash-test sheet against your contracted power rating and tolerance, and decide with your inspector whether witness testing or independent lab checks are warranted. Factory flash data, third-party sample tests and site yield simulations answer distinct questions; none replaces the others.

Read the warranty mechanics, not just the headline years

Ask for the full warranty text applicable to your specific module model and destination market. Separate the product workmanship warranty from the power-performance warranty terms. Check when coverage begins, who has standing to file a claim, what diagnostic records are required and whether the remedy is repair, replacement modules or financial compensation.

Then check how a claim works on the ground: who handles claims in the destination country, who pays sea and inland freight for replacements, who covers roof or ground-mount labour, and who backs the warranty if the trading company closes? Where a trading company is selling a third-party brand, confirm whether the manufacturer's warranty transfers to you. Headline durations do not cover logistics or labour unless the text says so.

Prevent transit damage between the factory floor and your warehouse

Clean inspection records will not protect panels from poor palletising or rough container stuffing. Specify packaging and container-loading rules that follow the module manufacturer's handling manual, including pallet IDs, stuffing records and arrival inspection procedures. LONGi's unpacking and handling guide illustrates common risks such as shifted pallets, crushed packaging and improper unloading. Because those rules are written for LONGi modules, obtain the specific manual for the brand you are buying.

Require container-loading photos, container and seal numbers where applicable, cargo insurance terms and a clear protocol for recording shortages or visible damage at unloading. Check notification rules with both the carrier and the insurer before shipment; claim filing windows vary by policy, carrier and trade lane.

Check destination import requirements separately

Quality records help assess the product being bought, but do not establish the complete import requirements in Nigeria, Kenya or other destination markets. Before the cargo departs, have your local clearing agent confirm the exact conformity assessment and customs documents required for the shipment. See our Africa solar-certification guide for how product certificates differ from import approvals, and our solar-logistics guide for transport planning.

What to include when requesting a quotation

When requesting a quote, share your destination country, order quantity, project application, target model or technical parameters, and final delivery location. If you already hold a supplier offer, attach the proposed datasheet and certificate set so missing documents can be spotted before you compare unit prices.

In a transaction for a Nigerian wholesaler, GoFair supplied A+ grade solar panels and assisted with or handled procurement, inland and international transport, cargo insurance, payment arrangements, and Form M and SONCAP documentation through to delivery. That project does not establish test results or warranty terms for any other order; your contract and quotation still need to spell out the exact inspection scope and responsibilities for your shipment.

Sources and scope limits

Sources checked on 25 October 2026. This article is a procurement document checklist, not a certification ruling, electrical engineering design or installation manual. Have a qualified specialist verify the specific module, intended application and current import regulations at your destination.